Lifts
involving two or more cranes are complex operations requiring skill and
detailed planning.
The
lift must be planned and carried out by skilled and qualified personnel under
the direction of an on-site qualified erection supervisor.
It
is necessary that a written detailed procedure (lift plan) be developed,
documented and kept on site. This procedure must be signed by the site
superintendent, the erection supervisor, the crane operators and the "signal persons" involved as evidence that the procedure has been reviewed, discussed
and understood by all workers involved in the operation. Any change in
procedures or personnel shall be documented and signed by all workers involved.
The
planned procedure should include the following requirements:
1.
Ground conditions must be stable, compacted and level.
(If
not, they must be corrected by blocking mats or compaction.)
2.
All cranes must rest on solid blocking.
3.
All cranes must be level.
4.
The weight and center of gravity must be determined exactly for the load being
hoisted.
5.
Longest load radius of each crane for the complete operation must be measured
exactly.
6.
Boom length and boom angles must be determined exactly.
7.
Rated capacity of each crane must be determined for the whole operation.
8. For a multiple crane lift, no crane should be loaded to
more than 75% of its net capacity.
9.
All cranes must be in good operating condition.
10.
The lead crane must be equipped with a load guage to ensure that the lift stays
within the safe operating conditions and lift plan.
11.
Consideration must be given to the symmetry and center of gravity of the load.
The load each crane will carry must be determined precisely.
12.
Swing and booming motions must be kept to a minimum.
13.
Wherever possible, the cranes should not travel with load. If travel is necessary,
then the cranes should have equal boom lengths.
14. Signal persons, riggers and operators must know
exactly what they have to do and what movements will have to be made before the
lift begins.
15.
Conduct a dry run without load.
16.
All communications during the lift should be made by radio (preferably closed
or hardline rather than walkie-talkie).
17. It is imperative that one person (the signal-
person) direct and control the operation.
That person should be positioned to view the total operation
and should maintain radio contact with the operators.
18.
One crane shall be designated the ‘lead’ crane taking instruction from the
signalperson. The other crane(s) shall follow, with the swing brake off. The
lead crane may shift from one crane to the other during the lift.
19.
All crane and load movements should be made as smoothly as possible. Brakes and
clutches should be applied gradually.
20.
Hoist lines must be kept vertical
at all times. This is absolutely critical.
When the lines are not vertical, the cranes are throwing extra load on each
other and may cause sideloading.
Note: Certain lifts such as cantilever type,
multiple crane, joining lead lines, and other specialized lifts, shall be
designed and supervised by a professional engineer.
No comments:
Post a Comment